Wyong Creek Bridge, Muswellbrook NSW
Project Description : Bearing Cover Design, Fabrication and fitting following Roller Rehab Bridge Bearing Service on 5th April, 2017.
Project Description : Bearing Cover Design, Fabrication and fitting following Roller Rehab Bridge Bearing Service on 5th April, 2017.
Project Description : Roller Rehab Bridge Bearing Service , 17th April, 2018. Bearing rust removal, internal cleaning, painting, greasing and oiling. Report on service and any defects identified. Mark bearings to gauge future movement. Ballast and debris on and around bearings on both abutments. Three bearing anchoring nuts were found to be loose. They were tightened on…
Project Description : Roller Rehab Bridge Bearing Service , 24th April, 2018. Bearing rust removal, internal cleaning, painting, greasing and oiling. Mark bearings to gauge future movement and report on service and any defects identified. Recently replaced pot bearings on both the abutment and next pier are in excellent condition. The rusted ‘nest of rockers’ bearing…
Rusted Gantries with severe crevice rust. Rusted gantry Structures were water/grit blasted to remove all rust All crevices and bare metal surfaces treated with crevice sealer. Gantries finally sprayed with two top coats of high metal content two pac paint.
Project Description : Roller Rehab Bridge Bearing Service. Bearing rust removal, internal cleaning, painting, greasing and oiling. Report on service and any defects identified. Bearings generally had surface rust only and required cleaning prior to servicing. Concrete bearing bed has lifted and cracked and requires a repair. Before and After. Bearings cleaned, de-rusted and coated.…
Rust removal and application of protective coatings to heavily rusted Brookes Street Bridge, Fortitude Valley Brooke street bridge was de-rusted and painted within a 38hr time frame in partnership between Action Corrosion & QLD Rail.Action Corrosion staff water grit blasting from a crane which is the preferred method when dealing with the possibility of lead…
Project Description : Roller Rehab Bridge Bearing Service , 19th – 22nd June, 2018. Bearing rust removal, cleaning, painting, greasing and oiling. Report on service and any defects identified. Rust remove and protect with Action Corrosion. Slide Plate Bearings and Pot Bearings. The slide plate bearings on this 27 span structure are in generally good condition.…
Project Description : Roller Rehab Bridge Bearing Service , 21th April, 2018. Bearing rust removal, internal cleaning, painting, greasing and oiling. Mark bearings to gauge future movement and report on service and any defects identified. Bearings are generally dry, rusted and covered in dirt and plant life. A slide plate bearing at the start of the truss which…
Project Description : Roller Rehab Bridge Bearing Service , 21th April, 2018. Bearing rust removal, internal cleaning, painting, greasing and oiling. Mark bearings to gauge future movement and report on service and any defects identified. The bearings on both abutment were covered in ballast, dirt and plant life. Once the top of the piers were cleaned…
Along the approaches there are small plates which appear to connect both the free expansion end and the adjoining fixed end of beams. A new walkway has been bolted to one side of the entire length of the structure. Whilst the handrail appears to have allowances for movement.